Why does concrete need 28 days to cure?
Concrete does not harden by drying. It hardens through a reaction that needs water and time, and 28 days is when the standards check the result.
Why does concrete need 28 days to cure?
Twenty-eight days is the age at which concrete strength is specified and tested in Australia. Concrete keeps gaining strength after that, but the 28-day test result shows whether a slab or footing reached the grade the engineer designed for. Curing in the first days after the pour keeps the concrete moist and warm enough for that strength to develop.
Twenty-eight days is the age at which Australian concrete is specified and tested for strength. A slab keeps getting stronger after that, but the 28-day result is the one the engineer designed around. It is the point where you can confirm the concrete under a building is what was ordered.
The concrete is not sitting idle while it waits. It gains strength the whole time, and the way it is looked after in those weeks decides how strong and how durable it ends up.
What curing does
Concrete does not harden by drying out. It hardens through a chemical reaction between the cement and the water in the mix, called hydration, and that reaction needs water and a reasonable temperature to keep going.
Curing is the work of keeping both in place. On site that means spraying or ponding water on the slab, covering it with plastic sheeting or wet hessian, or spraying on a curing compound that seals the surface so the water stays in.
Why the number is 28
In Australia, normal-class concrete is ordered by its strength at 28 days. AS 1379, the standard for specifying and supplying concrete, sets grades such as N25 and N32, where the number is the characteristic compressive strength in megapascals at that age.
Samples are taken from the truck on the day of the pour and cast into test cylinders, which a laboratory crushes at 28 days. The result shows whether the concrete reached its grade, and using the same age everywhere lets the supplier, the engineer and the certifier compare results on the same basis.
When curing is cut short
If the surface dries too early, hydration slows in the top layer. That layer ends up weaker and more porous than the concrete below it, and it is more likely to crack as it shrinks.
The top layer matters more than its thickness suggests, because it is the cover over the reinforcement. On an aggressive site, such as the ground described in building on saline and reactive soil in Western Sydney, it is what keeps water and salt away from the steel. AS 3600, the standard for concrete structures, sets a minimum curing period that gets longer as the exposure gets more severe.
Hot days and cold days
Weather changes how much care the curing needs. On a hot, windy day in Sydney the surface can dry out before the concrete has set and crack as it shrinks, so the finishers protect it from evaporation as soon as it is placed.
Cold weather brings a different problem. Hydration slows, the concrete gains strength more slowly, and the engineer allows for that before the slab carries load.
How the cure fits our programme
In Hybrid Volumetric Modular, the site works and the module fabrication run at the same time. We programme the site works back from the module delivery date, and twenty-eight days for the concrete to cure is built into that programme from the start.
So the cure does not hold up the modules. While the base structure gains its strength on site, the modules are being built and fitted out in the factory, so the wait happens alongside other work. The reasons the programme is shorter are set out in why the programme is shorter.
What the base has to be ready for
A module is set down onto the base structure, and the marriage between the two only works to the millimetre. By installation day the concrete has had its full curing time, and the base has been built to the same precision as the modules that land on it.
How the base is designed for the ground is covered in how foundations work when the building is built off site, and the lift itself in what happens on the day the modules are installed.
MADEmodular / MADEbetter.