What are development contributions in NSW?
Contributions are a cost of the consent, not of the building. They belong in the feasibility from its first version.
What are development contributions in NSW?
Development contributions are money, land or works a developer provides towards infrastructure such as local roads, parks and community facilities. In NSW they are charged as conditions of a development consent or complying development certificate, through section 7.11 contributions or section 7.12 levies to councils, the State's Housing and Productivity Contribution, or a planning agreement.
New development in NSW pays towards the roads, parks and other infrastructure it adds demand for, and those payments are called development contributions. They are charged when a project is approved, as conditions on a development consent or a complying development certificate.
A contribution can be paid as money, as land dedicated for infrastructure, or as works the developer builds in place of money. Division 7.1 of the Environmental Planning and Assessment Act 1979 sets out the four ways they are collected.
Section 7.11 contributions
A section 7.11 contribution is charged where development creates the need for infrastructure. The council works out what an area needs and what it will cost, and each development pays its share.
Two ideas set that share. Nexus is the link between the development expected in the area and the demand for new infrastructure, while apportionment makes sure new development pays only for the demand it creates.
A council can charge these contributions only under a contributions plan it has prepared and approved. The money can be spent only on what it was collected for, and a council that wants to charge above a set threshold needs the plan reviewed by the Independent Pricing and Regulatory Tribunal first.
Section 7.12 levies
A section 7.12 levy is simpler. It is charged as a percentage of the cost of the development, so it rises with the value of the work.
It needs no direct link between the development and the infrastructure it funds, although the plan has to show a general need for new infrastructure in the area. A levy can be charged each time a site is developed, except where a section 7.11 contribution was paid when the land was subdivided and the new development adds no demand beyond that.
The Housing and Productivity Contribution
The NSW Government collects the Housing and Productivity Contribution for state and regional infrastructure, such as state and regional roads, public transport, land for hospitals, schools and emergency services, and open space. It is charged on applicable residential, commercial and industrial development in Greater Sydney, the Central Coast, Illawarra-Shoalhaven and the Lower Hunter, complying development included.
It is charged on top of any council contribution, and it is calculated through the NSW Planning Portal as part of the application.
Planning agreements
A planning agreement is a contract negotiated between a planning authority and a developer. It can be used on top of the other contributions or in place of them. Neither side has to enter one, because a planning agreement is voluntary.
Exemptions
Development that needs no planning approval pays no contributions. Other development can be exempt through legislation, a policy or the contributions plan itself. Whether an exemption fits a project is checked against the current plan for that site.
Where they sit in a feasibility
Contributions are a cost of the consent and not of the building. They grow with the number of dwellings or the cost of the work, so they belong in the first version of a feasibility, alongside the planning pathway tested at project establishment and feasibility.
The NSW guide to infrastructure contributions says they are usually paid before someone can finish building or move in. The conditions to clear before building work starts are covered in what is a Construction Certificate in NSW.
A shorter programme does not change the contribution, which the consent sets. It shortens the period every other cost is carried, as set out in what are holding costs on a development and how Hybrid Volumetric Modular changes a development feasibility.