How does Hybrid Volumetric Modular change a development feasibility?

Programme length is a cost line, not just a schedule line. Compressing it changes the holding cost, the financing exposure and the date the asset starts producing income.

How does Hybrid Volumetric Modular change a development feasibility?

Site preparation and module fabrication run in parallel rather than in sequence, cutting build programmes by up to 60 percent. Every month removed is a month of holding and financing cost removed, and it brings the date the asset becomes income-producing forward by the same amount.

A feasibility is usually argued over land price, build cost and end value. Programme sits in the model as a schedule assumption rather than as a cost line, which is why its effect gets underweighted.

It is a cost line. It is one of the largest.

What a month of programme actually costs

Every month a project runs, it carries the cost of capital on the land and on drawn construction finance. It carries holding costs, rates, insurance, and the cost of the team overseeing it.

None of that produces anything. It is the price of the asset not being finished yet.

Then there is the other side of the same month. The asset is not producing income. For special-use accommodation with an operator waiting, that is a defined revenue stream that does not start until handover.

So a month of programme is charged twice. Once as cost incurred and once as income deferred.

Where the compression comes from

Conventional delivery is sequential. The site has to be prepared, then the structure goes up, then it is fitted out, then it is finished. Each stage waits for the one before it.

Hybrid Volumetric Modular splits that. Site preparation and module fabrication run concurrently rather than one after the other, which cuts build programmes by up to 60 percent.

The factory work is not waiting on the ground and the ground is not waiting on the factory. Two lines of work advance at once and marry at installation.

What that does to the model

Take whatever your feasibility carries per month for finance, holding and overhead, and multiply it by the months removed. That figure comes straight off the cost side.

Then move the income start date forward by the same number of months. On an income-producing asset that is a second, separate gain.

The two together are what change the answer, and they usually change it more than a variation in build rate would.

The headline cost question

The headline build figure can be higher than a conventional equivalent. That is the honest position and it is the first thing a developer should test.

What offsets it is the programme reduction, the lower holding and financing cost across a shorter exposure, and the earlier income start. Unit economics are quoted per project, because the balance shifts with the site, the finance structure and the type of accommodation.

The point is that comparing build rates alone compares one line of a model that has several.

Where it matters most

The effect scales with two things: how expensive your capital is, and how long the conventional programme would have been.

A project on cheap capital with a short programme sees a smaller difference. A project carrying expensive finance across a long conventional build sees the largest one, and those are usually the projects that were marginal on the conventional model.

For special-use accommodation there is a third factor. Prolonged approval and construction timeframes widen the gap between the point a need is identified and the point a built solution exists. Compressing the programme narrows that gap, and that is a risk reduction as well as a cost one.

What to model

Run your feasibility twice. Once on the conventional programme and once with the compressed one, with holding cost, financing cost and income start date all moving together.

The difference between those two models is the actual comparison. Comparing build cost alone is comparing the smallest of the three effects.

Start a conversation and we will work through the mechanics against your own numbers.

MADEmodular / MADEbetter.

MADEmodular / MADEbetter.

Let's talk.

Special-use accommodation, made better.