What is the critical path in a construction programme?

Most tasks on a programme can slip a little without moving the finish date. The tasks on the critical path cannot.

What is the critical path in a construction programme?

The critical path is the longest chain of tasks in a programme where each task waits on the one before it. It sets the earliest possible finish, so a delay to any task on that path moves completion by the same amount. Tasks off the path carry float, time they can slip without moving the finish.

Every construction programme has a chain of tasks that sets the finish date, and that chain is the critical path. Each task on it has to wait for the one before it, so the length of the chain is the shortest time the whole project can take.

That makes it the part of the programme to watch. A week lost on the critical path is a week added to the finish date, while a week lost on another task can often be absorbed.

How it is found

A programme lists every task, how long it takes and what it depends on. The slab cannot be poured before the footings are dug, and the linings cannot go on before the services are roughed in and inspected.

Link those tasks end to end and several chains appear across the project. The planner adds up each chain from start to finish, and the longest one is the critical path. This is the critical path method, and scheduling software does the sums once the tasks and their links are entered.

What float means

A task off the critical path has float, which is the time it can slip without delaying completion. Choosing the bathroom mirrors has plenty of it, while pouring the slab under a building usually has none.

Float is shared along a chain, so it gets used up. Once a chain has spent its float it becomes critical as well, which is why the programme is checked again every time a date moves.

On a conventional build

On a conventional build most of the work sits in one long line. The ground is prepared, the structure goes up, the building is closed in, the trades work through it and the finishes go on, with each stage waiting for the last.

Almost the whole build is on the critical path in that sequence. Rain on an open frame or a trade who does not turn up pushes the finish date back.

What building in parallel changes

In Hybrid Volumetric Modular, the modules are built and fitted out in a climate-controlled factory while the site is prepared. Two long chains that would sit end to end now sit side by side, and the critical path becomes the longer of the two, followed by installation and completion.

That overlap is where the programme reduction of up to 60 percent comes from, as explained in how the overlap shortens the programme. We programme the site works back from the module delivery date, with 28 days for the concrete to cure built in from the start.

What stays on the path

Design and approvals sit ahead of both chains, so they stay on the critical path whichever method builds the dwellings. Authority connections for water, sewer and power often sit there too, because the applications take time and the site cannot be finished without them. That is why they start early, as set out in utility connections and authority approvals.

The factory chain has its own critical tasks. Each module has to be finished, checked and ready on the day the base structure is ready to receive it.

Why it matters to a feasibility

Every month on the critical path is a month of interest, rates, insurance and site costs. A shorter path shortens the period those costs are carried, and it brings forward the date the building can start earning income. How those costs are modelled is set out in what are holding costs on a development.

A lender reads the programme the same way. A critical path with fewer outdoor tasks on it gives weather and trade shortages fewer chances to move the finish date, a point covered in how much programme risk does weather actually carry.