What is novation in a design and construct contract?

Novation hands the design team from the client to the builder partway through a project. That handover is where design responsibility has to be pinned down.

What is novation in a design and construct contract?

Novation replaces one party to a contract with another, with everyone's agreement. In design and construct, the client engages designers to take the design to an agreed stage, often development approval, then novates their contracts to the builder. From then on the designers work for the builder, who completes the design and answers for it.

In a design and construct contract, novation moves the designers from the client's side of the project to the builder's. The client engages an architect and consultants to develop the design to an agreed point, and then their contracts are transferred to the builder, who finishes the design and builds it.

The word comes from contract law. A novation replaces one party to a contract with a new one. It needs the agreement of all three parties, so it is done by a deed of novation signed by the client, the designer and the builder.

Why projects use it

Novation tries to give a client two things at once. Early on, the client wants control of the design, to set the quality and to win planning approval with an architect working for them. Later, the client wants one party responsible for the finished building.

So the client's own team takes the design through the early stages, and the builder takes over that same team for the construction documents and the build. AS 4902, the Australian Standard general conditions for design and construct, is one of the contract forms these arrangements are written around.

When it happens

The point of novation is a decision in the contract. On many projects it comes after development approval, and on others after part of the construction documentation is finished.

The later it happens, the more of the design the client has controlled, and the less room the builder has to shape the design around how it will be built. That trade is the main thing to weigh when the point is chosen.

What changes for the designer

After novation, the designer's client is the builder. The builder pays the fees and directs the work, and decisions about cost and buildability now come from the builder's side of the table.

That is the purpose of the arrangement, since the builder needs control of the design to carry the risk for it. It is also why clients often keep a right to approve changes to the parts of the design they care most about, such as the plan and the external materials.

Where the risk sits

The builder takes on a design it did not start. If the design it inherits has an error, or does not match the client's brief, the contract decides who pays to fix it, and that question is best settled before the deed is signed.

On special-use accommodation the stakes are higher, because the requirements are exacting and a design error can be a compliance error. A bathroom drawn a few millimetres short of a dimension in the SDA Design Standard can hold up the dwelling's certification.

What to check in a deed of novation

Start with who is responsible for design work done before the novation date. Some deeds keep the designer's duty to the client for that early work, and others transfer everything to the builder.

Then check which documents the builder has to design to, how changes to the client's requirements are handled, and how the record of earlier design decisions travels with the project. That record includes any SDA design assessment, and a design certificate only helps if the building matches it, as set out in how do you build an SDA dwelling in NSW.

When there is nothing to novate

With us, design, certification and construction sit inside one accountable business from feasibility to handover.

Construction input flows through the design from the start, as described in what is Early Construction Involvement, and SDA assessment and review are built into the design stages instead of being added at the end. The wider case for the model is in what does design and construct delivery actually mean.

MADEmodular / MADEbetter.

How we deliver. Discuss your project.

MADEmodular / MADEbetter.

Let's talk.

Special-use accommodation, made better.