What is an inspection and test plan?

An inspection and test plan decides, before the work starts, what will be checked, when, by whom and against what.

What is an inspection and test plan in construction?

An inspection and test plan, or ITP, is a document that lists the inspections and tests a piece of work has to pass, in the order they happen. For each check it sets the acceptance criteria, the reference document, who is responsible and the record kept. Hold points stop the work until a check is signed off.

Before a piece of work starts, an inspection and test plan, or ITP, sets out every check it has to pass, in the order the work is done. Everyone involved knows in advance what will be inspected, when, by whom and what counts as a pass.

Each trade or activity usually has its own ITP, so waterproofing has one and the electrical installation has another. Together they form the quality record of the building.

What an ITP lists

A typical ITP is a table. Each line is one check, and the columns set out the activity, the reference document such as a drawing, a specification or an Australian Standard, the acceptance criteria, the method of checking, how often it happens, who is responsible and the record kept.

The acceptance criteria are the heart of it. A line that says "check the shower" is not a criterion, while a fall to the floor waste, measured and recorded before the tiles go down, is one.

Hold points and witness points

Some checks are hold points. Work cannot go past a hold point until the check is done and signed off, because the next step would cover it, such as closing a wall over plumbing that has not been pressure tested.

Others are witness points. The person responsible is told in advance and can attend, but the work carries on if they choose not to. Deciding which checks are holds and which are witnesses is one of the main decisions in writing an ITP.

Who signs

The person doing the work usually checks it first, and a supervisor or quality manager then verifies it. For some items a consultant such as the structural or hydraulic engineer signs as well.

The principal certifier carries out its own inspections at set stages of the work. An ITP does not replace those inspections. It is the builder's own system, and its purpose is that the work is right before the certifier arrives. Certification of factory-built work is covered in who certifies a building constructed in a factory.

Checks in a factory

A factory suits this kind of plan well, because work happens at fixed stations in a set sequence. Each check sits at the same point in the process for every module, and it happens before the next layer closes the work in.

Our modules are built to a zero-tolerance standard in a climate-controlled factory. The frame is checked for dimension while it is open, the bolted connections are inspected while they can be seen, and the services are tested before the linings go on, as described in how is quality controlled in a factory build.

Two sets of checks, one tolerance

In Hybrid Volumetric Modular, the base structure on site carries its own checks, and those have to agree with the factory's. The base is set out to the same precision as the modules, because the marriage between the two only works to the millimetre.

The record at handover

A signed ITP is evidence. The certifier sees what was checked and when, and years later an owner can still see what sits behind each wall after the linings were closed.

Those records go into the handover package with the as-built drawings, as set out in handover documentation and as-built records.