Building in a mine subsidence district in NSW

A declared mine subsidence district adds an approval and a set of building limits. They are worth finding before the design is drawn.

What do you need to build in a mine subsidence district in NSW?

You need approval under the Coal Mine Subsidence Compensation Act 2017 before work starts, unless the work is exempt. Each property has a surface development guideline, which can limit building size and construction type. Councils and certifiers can approve compliant work under some guidelines. Subsidence Advisory NSW assesses everything else.

Before you build in a declared mine subsidence district in NSW, you need approval under the Coal Mine Subsidence Compensation Act 2017, and each property carries its own guideline that sets what can be built. Subsidence Advisory NSW manages the system, and the checks belong at feasibility, before the design is drawn.

These districts cover land where planned, active or old underground coal mining could cause the surface to move. Nothing on the surface tells you, so the check is a search rather than a site visit.

Where the districts are

Subsidence Advisory NSW lists the districts on its website. They include Newcastle, Lake Macquarie, East Maitland, Maitland West, Branxton and Muswellbrook in the Hunter, and Wyong on the Central Coast.

South-west of Sydney there are Appin, Wilton, Picton, Bargo and South Campbelltown. Further out, the list includes Lithgow and Mudgee.

The maps give an overview only. To check a property, search the address on the NSW Planning Portal spatial viewer, which shows whether the land is in a district and which guideline applies to it.

How the guidelines work

Each property is assigned a surface development guideline, based on the risk at that spot. Two neighbouring lots can have different guidelines, so a nearby approval tells you little.

The guidelines run from no restrictions through to high predicted subsidence impact. A compliant application under Guidelines 2, 3, 3A, 6 or 8 can be approved by a council or a registered certifier without referral. Guidelines 1, 1A, 4, 5 and 7 need approval from Subsidence Advisory NSW.

A design outside its guideline goes to merit assessment, where Subsidence Advisory NSW can attach conditions covering building size, location, materials and construction methods.

What a guideline can limit

Guideline 2 shows the kind of limits involved. It allows up to two residential buildings of one or two storeys in brick veneer, with limits on length and footprint, on reinforced concrete footings or a slab to AS 2870, with masonry articulated to suit.

It also rules out basements, integral retaining walls, and suspended or stepped slabs. More than two residential buildings, or a commercial building, goes to merit assessment.

Those details matter on a special-use project. A multi-dwelling site can pass the two-building limit quickly, and a stepped or suspended base is a common way to reach a level entry on a sloping block. Finding that out at feasibility can change the site plan, as covered in site constraints that decide modular viability.

How it fits the approval

Under the Environmental Planning and Assessment Act 1979, development in a district that is not exempt is integrated development, so a council refers the application to Subsidence Advisory NSW. An application can also go straight to Subsidence Advisory NSW through its portal.

Small works such as some carports, decks and fences are exempt. A new dwelling is not.

This approval sits alongside the planning pathway set out in planning pathways for special-use accommodation in NSW, so the two are planned together.

What it means for a modular build

A guideline is written around the finished building and its footings, so a modular building is assessed the same way as any other. The frame's over-engineering is not a substitute for that approval, and we do not treat it as one.

The base structure is where most of the response happens. In Hybrid Volumetric Modular it is built on site to suit the ground, so the footing design answers the guideline and the geotechnical report together, as covered in how foundations work when the building is built off site. The split between factory work and site work is set per project, and a subsidence guideline is one of the things that sets it.

Why the approval protects the owner

Homes and buildings in NSW can be eligible for compensation if mine subsidence damages them, and Subsidence Advisory NSW makes that conditional on the correct approvals having been obtained. Building without one puts that protection at risk, along with the project.

MADEmodular / MADEbetter.

Our standards. Discuss a project.

MADEmodular / MADEbetter.

Let's talk.

Special-use accommodation, made better.